Building a new home this summer, will not build pool for a year or more but the decks and retaining walls around the pool area are going in next month. I'd like to bury pipes under the slab now, stub out the PVC in the area where the pool will go, and cap the lines so they're in place when it's time to build the pool.
I have soils analysis and structural engineering in hand so have a good idea of pool construction parameters, but I haven't hired a pool designer yet because it will be at least a year before I can afford to get the pool started. I want to run 2" PVC conduit under the concrete deck now, though; it will be a lot cheaper to complete the trenching before the concrete is poured! Problem is, I don't know how many pipes i need to run, and I'd like to confirm that 2" is the correct size for suction/return lines.
Here are the design parameters:
- pool will be 20' x 30' , shallow end 3' and deep end 7'. Total gallons approximately 21,000 after allowing for steps and 'tanning ledge'.
- negative/vanishing/infinity edge on the 20' (deep) end of the pool; catch basin will hold approximately 800 gallons/100cf of water and will have a separate pump from the primary pool filter pump (I would expect to run one or the other depending on whether the Vanishing Edge effect is being used?)
- poolhouse equipment location is known, and slab will be poured at the same time as the deck; it's 36 feet away - from the center of the nearest edge of the pool (and at the same elevation as the surface of the pool).
Based on the "6 hour rule", I should be circulating about 58gpm from either the catch basin pump or the primary filter pump; I picked 2" pipe because it seems like it meets the maximum 6fps requirement for a 60gpm flow. Is there a a material benefit to stepping up to 2-1/2" suction pipe? The marginal cost isn't much, but I don't want to waste money if it isn't needed.
So - how many pipes do I need, and do they all need to "home run" to the equipment area, or can i combine all the suctions and all the returns into manifolds and only run two pipes for each pump under the concrete?
Has anyone seen a 'pool plumbing for dummies' somewhere on this site, or elsewhere on the web? Apologies for the newbie questions, but I don't know much/anything about pool construction and the concrete trucks aren't all that far away.
Thanks in advance,
SRCal
Bookmarks