+ Reply to Thread
Results 1 to 10 of 10

Thread: Constructing 12x24x54 AG on our own... are we done yet?

Hybrid View

  1. #1
    matt4x4 is offline Lifetime Member Verb Herder matt4x4 2 stars matt4x4 2 stars
    Join Date
    Dec 1969
    Location
    .
    Posts
    819

    Default Re: Constructing 12x24x54 AG on our own... are we done yet?

    Remember you'll need a good 1.5" ABOVE the skimmer before backwashing or you'll just suck air because water won't replenish the skimmer fast enough - one way to "cheat" is to remove the weir, gets you an extra 1/2" of fast water.
    You can also try to backwash early with the pool vac hose connected into the skimmer (no basket), and held under water, with the garden hose water "sealing" the connection inside the skimmer - flow will be slower, but it should remove the zeo dust as per it's purpose.

    If you backwash all your water out and can't go to filter right away due to low water, set the manual vacuum into the pool, connect the hose into the hole in the bottom of the skimmer (no basket), and place your garden hose inside the skimmer - this will keep a seal around the hose while sucking the crap off the bottom of the pool and will give you a little head start to you can stay on track with your tight schedule.

    Your Granules won't dissolve very fast (esp. in cold water), so don't measure chlorine within half an hour of dispersing. I'd recommend using bleach to start just so it disperses fast, put in only about 1/2 gal @ 6% for your size pool if people are going swimming, outside of that just worry about your pH. Stabilizer just saves your chlorine from sunlight, alkalinity is rarely an issue - esp with AG pools - unless your hose water is questionable.

    Your CYA will need several days to a week before it gives you any sort of indication (very slow at dissolving) - place it in a sock and tie it off the stairs or else it will harm liner.
    Last edited by matt4x4; 07-04-2007 at 03:27 PM.

  2. #2
    zephans is offline Registered+ Thread Analyst zephans 0
    Join Date
    Jun 2006
    Location
    Bothell, WA
    Posts
    56

    Default Re: Constructing 12x24x54 AG on our own... are we done yet?

    FINAL UPDATE:
    The skimmer went in without too much problems (see related skimmer thread for details). We opened on 4th of July as I hoped. I still have a clear pool despite not using the filter yet. The kids love the pool.

    PROBLEMS:
    1. We have a 13.5'x23.5' pool! This is blocking installation of top rails. (I'll post details and related questions in separate thread shortly.)
    2. First backwash still pending - I'm noodling out where to dump waste water and how to reclaim or put the water to best use. (See related backwash thread for details & status.)
    3. Ladder is unstable and hard to raise/lower. I'll figure that out with a little time and enginuity (or more $$$ for better ladder).
    4. Water is still COLD!!! Solar panel installation is next as soon as I get filter and top rails done.
    5. Deck extension would be great... but I haven't even started designing or constructing it yet... water first.


    LESSONS LEARNED:
    #1: Walk through each step you will do and make sure you know how to do each step. If you have questions post questions before you are blocked.

    TIP: If you have a question or are stuck remember to search this forum before posting. Often you will find the answer already posted. I recommend 10min "quick search" before posting.

    #2: If a measurement doesn't match manufacturer instructions or your expectation stop and figure out why. Fixing before wall, sand, and liner are installed is MUCH easier.

    #3: Mark out pool area to excavate INCLUDING 2' extra on all sides. For example, my 12x24 requires 16'x28' are to be constructed properly.

    #4: Estimate time you will spend for each step before you begin entire project. You will get much more realistic picture of construction time than if you just plan to take a weekend. Even if you aren't short on time this is useful for planning when you need sand (pickup or delivery), when you should expect to be at each stage, and when to ask friends/family over for a pre-pool party.
    Thanks! -ZephanS
    AG BF 13.5'x23.5'x54" (wups) Diamond Star (Wil-bar) purchased 5/30/2007 from sunenterprises.com. 2hp pump + 150lb sand filter (both WaterWay combo) using 75lbs zeobrite + SWG.
    Dug and built ourselves in ~30hrs by ~7/4 thanks to PF (esp. hrdennis,nwmnmom,matt4x4,Waste,CarlD, &others). ~$5,500 total cost.

  3. #3
    NWMNMom is offline Registered+ Widget Weaver NWMNMom 0
    Join Date
    Nov 2004
    Location
    WAAAY NW Minnesota
    Posts
    461

    Default Re: Constructing 12x24x54 AG on our own... are we done yet?

    I am so glad you all are going to have this great pool to enjoy for years to come!!! We want more pictures!!!
    Beats driving to the lake!
    18'x33'x52" AG oval, hard plumbed system, 22" Pentair Meteor Filter 1.5hp pump, Goldline SWCG System, 2/4x20 SolarBear Panels, Biltmore Steps - 16x14' composite deck, Pool Rover Jr

+ Reply to Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts