Days 25 & 26 - 3/16 & 3/17
We had some rain on days 23 and 24 and that delayed the Pebble Tec install.
On Friday 3/16 the rock guys started work on the flagstone inlays, firepit and bench. On Saturday 3/17 the Pebble Tec got installed and the outdoor kitchen was delivered.
Firepit and bench in progress - You can see some of the inlays to the side of the fire pit but they are covered in stone dust.
Another shot of the fire pit and bench
Setting up for the Pebble Tec. This was very cool to watch. They had ropes running the length of the pool to hang their water sprayers and rollers.
Spraying it in
Washing off the mortar to expose the pebbles.
Continued in next post