+ Reply to Thread
Results 1 to 10 of 58

Thread: Steve's pool build status - Work started 2/19/2007!

Hybrid View

  1. #1
    skamp is offline Registered+ Thread Analyst skamp 0
    Join Date
    Aug 2006
    Location
    Cypress, TX
    Posts
    94

    Default Re: Steve's pool build status - Work started 2/19/2007!

    Days 18, 19 & 22 - 3/9, 3/10 and 3/13

    During this time they formed and poured my decking. They did the pouring last night and it starting raining. These poor guys were out there until 8:00 PM under plastic finishing up. The low parts of the decking around the perimieter and in other places is where the flagstone inlays will go.

    Forming the decking - You can also see the patio cover is completed.



    Entry into the side of the pool



    Spreading the pea gravel



    Floating the concrete



    Finishing up and getting all the expansion joints in



    I did not take any pictures of them exposing the pea gravel after the concrete set up but it was cool to watch the decking come to life. Today they are doing the pool cleanup and tomorrow the pebble tec goes in! Looks like the pool will be getting filled this weekend.

    Steve

  2. #2
    Join Date
    Dec 1969
    Location
    the woodlands, texas.
    Posts
    82

    Default Re: Steve's pool build status - Work started 2/19/2007!

    Congrats, everything is looking great and your on a really good turn.

    If I were to point out anything I'd object to, as a contractor, it would be your posts.
    An ACQ 60 4"x6" post could have been incorporated into your covered porch and then wrapped with Hardee siding or Western red Cedar. It would finish a lot cleaner than the treated pine posts that currently hang out further than your beams.
    If you were to wrap the post now they would finish out much wider than the beam. I'm not knocking the way they did it, but I'd encourage you to have them trim the top up to the soffit to make it a little more eye appealing than the way it is now. The 6x6 post butting up to and hanging out wider than the 4" beam just has a rough uncompleted look to it. This will be much more noticeable after painting than it is now.

    just my .02

    See ya,
    Kelly

  3. #3
    skamp is offline Registered+ Thread Analyst skamp 0
    Join Date
    Aug 2006
    Location
    Cypress, TX
    Posts
    94

    Default Re: Steve's pool build status - Work started 2/19/2007!

    Quote Originally Posted by huskyrider View Post
    Congrats, everything is looking great and your on a really good turn.

    If I were to point out anything I'd object to, as a contractor, it would be your posts.
    An ACQ 60 4"x6" post could have been incorporated into your covered porch and then wrapped with Hardee siding or Western red Cedar. It would finish a lot cleaner than the treated pine posts that currently hang out further than your beams.
    If you were to wrap the post now they would finish out much wider than the beam. I'm not knocking the way they did it, but I'd encourage you to have them trim the top up to the soffit to make it a little more eye appealing than the way it is now. The 6x6 post butting up to and hanging out wider than the 4" beam just has a rough uncompleted look to it. This will be much more noticeable after painting than it is now.

    just my .02

    See ya,
    Kelly
    Kelly,
    The 6x6 beams are going wrapped in a 15" brick column. I left 5 1/2" between the post and the gutter downspout. If I was going to have exposed beams I would have done it very different. I had to wait until the deck was done for them to do the columns. Thanks!

    Steve

  4. #4
    skamp is offline Registered+ Thread Analyst skamp 0
    Join Date
    Aug 2006
    Location
    Cypress, TX
    Posts
    94

    Default Re: Steve's pool build status - Work started 2/19/2007!

    Days 25 & 26 - 3/16 & 3/17

    We had some rain on days 23 and 24 and that delayed the Pebble Tec install.

    On Friday 3/16 the rock guys started work on the flagstone inlays, firepit and bench. On Saturday 3/17 the Pebble Tec got installed and the outdoor kitchen was delivered.

    Firepit and bench in progress - You can see some of the inlays to the side of the fire pit but they are covered in stone dust.



    Another shot of the fire pit and bench



    Setting up for the Pebble Tec. This was very cool to watch. They had ropes running the length of the pool to hang their water sprayers and rollers.



    Spraying it in



    Washing off the mortar to expose the pebbles.



    Continued in next post

  5. #5
    skamp is offline Registered+ Thread Analyst skamp 0
    Join Date
    Aug 2006
    Location
    Cypress, TX
    Posts
    94

    Default Re: Steve's pool build status - Work started 2/19/2007!

    There she is waiting to get acid washed.



    Closeup of the tanning ledge



    Here is the outdoor kicthen. It still needs to be assembled and leveled. Once that is done the countertop and stone work needs to get done.



    View from the back. It will have a grill, fridge, sink and side burner. It came on 3 pallets and weighed 1290 lbs!



    Today they are acid washing the pool and starting the fill. It is getting close now.

    Steve

  6. #6
    Join Date
    Jun 2006
    Location
    Northern Kentucky
    Posts
    174

    Default Re: Steve's pool build status - Work started 2/19/2007!

    I think your outdoor kitchen is bigger than my ONLY kitchen!!

    Looking great... betcha can't wait for summer!!
    ~Grace

    Avid reader of this forum
    but alas, no pool... yet!

  7. #7
    skamp is offline Registered+ Thread Analyst skamp 0
    Join Date
    Aug 2006
    Location
    Cypress, TX
    Posts
    94

    Default Re: Steve's pool build status - Work started 2/19/2007!

    Quote Originally Posted by GraceByDesign View Post
    I think your outdoor kitchen is bigger than my ONLY kitchen!!

    Looking great... betcha can't wait for summer!!
    The sad thing is it is bigger then mine as well. The outside of my house is now much nicer then the inside!

    Steve

+ Reply to Thread

Similar Threads

  1. Deer in Scuba Steve's pool
    By DJK555 in forum Pools, Pets and Creepy Critters
    Replies: 1
    Last Post: 09-28-2010, 05:19 PM
  2. Welcome year 2007 agp newbies
    By hrsdennis in forum Above-Ground Pool Construction & Repair
    Replies: 4
    Last Post: 03-21-2007, 06:03 PM
  3. Steve's pool project 1-24-07
    By skamp in forum In-Ground Pool Construction and Repair
    Replies: 49
    Last Post: 02-20-2007, 01:30 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts