Days 11 & 14 - 3/2 & 3/5
On Friday they finished the rock work and started the patio cover (different company). Overall the rock work far exceeded my expectations. It looks awesome. There are two small problems with the rock work. First they installed a few rocks on top of the spa even though we did not want them. They said they will fix it and replace it with flagstone. Second, the chip work on some of the flagstone edge does not look very nice. It looks like teeth instead of the normal random chipped look. They said they will fix that as well. They got a late start on the patio cover due to the support beams not showing up until 12:30. They started at 7:30 and put on the 6x6 posts and basically sat around until the beams showed up.
On Monday they did all the electrical. They ran 100 AMP's to my control panel and I have 2 1" breaker slots and 3 relays left for low voltage lighting. The almost completed the patio cover as well.
I was told they may start working on the decking today. If that is the case we really only have decking and the Pebble Tec left. That is insane! I will post pictures later today.
House before patio cover
Framing the cover
Getting close
Rock work done (right side)
Rock work done (left side)
Steve