    Can anybody comment on the proper time/sequence in the construction process to pour the collar and the vermiculite bottom on a IG steel-walled vinyl liner pool?

    I noticed a neighbor's vermiculite bottom is already in-place, but the collar hasn't been poured yet. That seems out of sequence to me (based on my own pool's building and a couple of other neighborhood pools I'd seen). I'm wondering if its worth bringing to the neighbor's attention?

    My understanding (which may be wrong) was that the collar needed to be poured and inspected before the bottom goes in -- just in case the inspector (or even the contractors) noticed a problem with the walls/bracing. Any potential problems in doing the bottom before the collar?

    TIA

  2. #2
    Join Date
    Jul 2006
    Posts
    92

    Default Re: Construction Sequence?

    Just had mine done-

    collar was poured , vermiculite bottom and liner all done in the same day.
    inspections 2 days later!

  3. #3
    Waterworks is offline In the pool biz Thread Analyst Waterworks 0
    Join Date
    Dec 1969
    Location
    .
    Posts
    94

    Default Re: Construction Sequence?

    We just did the collar and pool bottom at the same time on a pool this afternoon. We normally do the collar first, then the bottom immediately afterward, but it doesn't make much of a difference. The only problem is if you aren't careful pouring your collar, the walls can move and disturb the bottom. As long as you are careful pouring the collar, there should be no problems.

    Brad
    Waterworks Pools

+ Reply to Thread

Similar Threads

  1. new construction
    By kenny6269 in forum In-Ground Pool Construction and Repair
    Replies: 21
    Last Post: 06-08-2013, 03:38 PM
  2. New Pool Construction
    By cliffleblanc3 in forum In-Ground Pool Construction and Repair
    Replies: 3
    Last Post: 10-14-2011, 08:15 PM
  3. Liner in and filling, need right gasket sequence for skimmer
    By scootchu in forum Above-Ground Pool Construction & Repair
    Replies: 3
    Last Post: 08-15-2006, 01:58 PM
  4. Refilling - What is the sequence I should use to adjust chemistry
    By Slam Pool Guy in forum Testing and Adjusting Pool Water Chemistry
    Replies: 3
    Last Post: 07-25-2006, 02:02 AM
  5. construction
    By Archer in forum In-Ground Pool Construction and Repair
    Replies: 1
    Last Post: 07-24-2006, 09:36 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts