Closed Thread
Results 1 to 9 of 9

Thread: Suggested payment schedule?

Hybrid View

  1. #1
    Join Date
    Apr 2006
    Posts
    7

    Default Re: Suggested payment schedule?

    We just signed a contract yesterday with the following schedule.

    60% after gunite is complete
    35% after tile, coping decking complete
    5% when we swim.

  2. #2
    SPitz Guest

    Default Re: Suggested payment schedule?

    Ours was:

    30% after excavation and forming
    30% after gunite
    30% after tile and coping
    10% when we swim

  3. #3
    Join Date
    Dec 1969
    Location
    Arlington, VA, USA.
    Posts
    11

    Default Re: Suggested payment schedule?

    Thanks for all the helpful suggestions, folks. Since I'm building in the pool at the same time as a new house, and am financing the whole she-bang with a construction loan, I realized I need to build in time for draw requests and inspections. So after reviewing these responses (and those received on another forum) I've gone back to him proposing the following.

    $1000 at time of contract.
    30% of balance within 10 days after completion of excavation.
    25% of balance within 10 days after completion of installation of steel, plumbing and gunite.
    20% of balance within 10 days after completion of installation of tile, coping and parging of exposed exterior of bond beam.
    15% of balance within 10 days after completion of plaster.
    Final 10% of balance within 10 days after satisfactory completion of all punch-list items and receipt of satisfactory evidence of release or waiver of all liens, including by all subcontractors and suppliers.

    He's uncharacteristically silent, so we'll see if he moves at all. I do have another confidence-inspiring builder whose bid was very similar, so I do have options.

  4. #4
    Join Date
    Apr 2006
    Location
    Spring, Texas
    Posts
    4

    Default Re: Suggested payment schedule?

    Hi,

    Just for comparison, my pool builder had us pay as follows:

    No money up front
    35% after gunite
    30% after pumbing
    25% after decking
    10% after water was circulating and we are swimming.


    Michelle

  5. #5
    ivyleager is offline Lifetime Member Weir Watcher ivyleager 0
    Join Date
    Dec 1969
    Location
    North Carolina
    Posts
    149

    Default Re: Suggested payment schedule?

    Mine was a IG vinyl pool (18x36), w/ tons of extras. Brick coping/edging at ALL corners had to be redone, which set us back 4 weeks.

    Schedule was as follows:
    5% at signing contract
    55% when hole dug (on a Tuesday)
    30% when liner in and water in pool (by Friday)
    10% upon completion: coping, deck, ladders, diving board, water level maintained and filter running......basically able to swim.
    *****originally had stated only that completion was 'filled w/ water and filter running' which means cleared by inspector. We said no to that, as brick redo and then cement decking was delayed. Builder was fine w/ this change in original contract.

    Good luck.

    CaryB

  6. #6
    CarlD's Avatar
    CarlD is offline SuperMod Emeritus Vortex Adjuster CarlD 4 stars CarlD 4 stars CarlD 4 stars CarlD 4 stars CarlD 4 stars CarlD 4 stars
    Join Date
    Dec 1969
    Location
    North Central NJ
    Posts
    6,607

    Default Re: Suggested payment schedule?

    Having been burned by a kitchen contractor when the final payment was 5% (he forfeited it to avoid finishing and I had to do all the final work myself), I'd never settle for less than "10% upon passing inspection" again, and try to get 25% if I could.

    I'm even willing to escrow the money (with MY attorney) so that he knows it's there and I can't stiff him, but if he doesn't meet specified conditions, it doesn't get released.
    Carl

Closed Thread

Similar Threads

  1. Suggested Sticky Topic
    By jhm in forum Using Chlorine and Chlorinating Chemicals
    Replies: 2
    Last Post: 07-10-2010, 08:54 PM
  2. Suggested on-line vendor for pump motor
    By GreenLight in forum Pool Equipment & Operations
    Replies: 0
    Last Post: 07-06-2009, 07:43 PM
  3. Cell cleaning schedule.
    By Phillbo in forum Salt Generators (SWCG) & other Chlorine Feeders
    Replies: 8
    Last Post: 10-03-2006, 08:26 AM
  4. Winter Pump Schedule ??
    By roll tide in forum Pool Equipment & Operations
    Replies: 1
    Last Post: 09-21-2006, 09:55 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts