    Default Re: eljefe281's (Jeff's) pool project

    Quote Originally Posted by SeanB. View Post
    Is your plaster scheduled too?
    Monday or Tuesday.
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  2. #42
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Decking poured yesterday.









    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  3. #43
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project







    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  4. #44
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project







    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  5. #45
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Plaster complete.

    Pool filling (with help from Mother Nature).
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  6. #46
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Pool is full! Woo hoo!
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  7. #47
    SeanB. is offline --General User-- Weir Watcher SeanB. 0
    Join Date
    Aug 2006
    Location
    Missouri City, Texas
    Posts
    207

    Default Re: eljefe281's (Jeff's) pool project

    Awsome! Now, where's the picture?
    Site owner -- www.troublefreepool.com

  8. #48
    No Need is offline Registered+ Thread Analyst No Need 0
    Join Date
    Aug 2006
    Location
    San Dimas, Ca
    Posts
    57

    Default Re: eljefe281's (Jeff's) pool project

    Quote Originally Posted by SeanB. View Post
    Awsome! Now, where's the picture?
    Yeah! Where's the Pics? lol

  9. #49
    Join Date
    Apr 2006
    Location
    Scottsdale, Arizona
    Posts
    526

    Default Re: eljefe281's (Jeff's) pool project

    Nice looking layout!! Is there an easement at the back of your yard that prevented you from setting the pool farther back to provide a bigger patio area up against the house?
    14'x31' kidney 21K gal IG plaster pool; SWCG (Saline Generating System's SGS Breeze); Pentair FNS Plus 48 DE DE filter; Whisperflow 1 HP pump; 8 hours hrs; kit purchased from Ben; utility water; summer: none; winter: none; PF:5.7

  10. #50
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Quote Originally Posted by Phillbo View Post
    Nice looking layout!! Is there an easement at the back of your yard that prevented you from setting the pool farther back to provide a bigger patio area up against the house?
    Yes, there is. Eight feet.
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

+ Reply to Thread

Similar Threads

  1. Pool project
    By Smokey in forum --cleanup--
    Replies: 1
    Last Post: 10-02-2012, 12:04 PM
  2. AL's Pool Project 10-17-06
    By No Need in forum In-Ground Pool Construction and Repair
    Replies: 45
    Last Post: 04-08-2007, 09:06 AM
  3. Subcontracting your own pool project?
    By minddeal in forum In-Ground Pool Construction and Repair
    Replies: 14
    Last Post: 02-28-2007, 09:15 PM
  4. Steve's pool project 1-24-07
    By skamp in forum In-Ground Pool Construction and Repair
    Replies: 49
    Last Post: 02-20-2007, 01:30 PM
  5. That massive pool restoration project
    By peppercorn in forum In-Ground Pool Construction and Repair
    Replies: 8
    Last Post: 01-04-2007, 09:10 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts