Re: eljefe281's (Jeff's) pool project
It's starting to look like something, with most of the coping in place.
I feel sorry for my poor builder. I strongarmed him into ordering custom, double bullnosed coping pieces for the top of the raised beam and around the spa so we wouldn't have seams running lengthwise. There was some sort of miscommunication and not enough pieces got ordered, so now he's going to have to remobilize the coping guy next week.
It amazes me that this guy doesn't blink an eye when something like this happens.
There must be a whole lot of contingency in the contract price.
Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.