I should have said click on video to play
Printable View
I should have said click on video to play
No kidding --- WOW!! That is quite an extensive project! The image of what the finished results will be like is just gorgeous!
Thanks watermom. If you click on the image the video starts. I see your puppies' in your Avatar, here is a picture of ours.
http://i814.photobucket.com/albums/z...psd077d111.jpg
Travertine pavers being installed on two sets of stairs. They will start the other side next week.
http://i814.photobucket.com/albums/z...psd1bdb07d.jpg
http://i814.photobucket.com/albums/z...ps7e51f02a.jpg
What is your estimated completion date?
We are entering the 9th month of construction. I expect the pool to be up and running in about two weeks. I also expect it to take another 8 weeks to get the audio/visual, landscaping, lighting, irrigation, and perimeter walls stucco and stoned
If you can, please take some pictures when the finish is applied, and when the equipment is installed.
I've been researching surge protection, in another thread. If you have thunderstorms in your area, you may want to take a look at this thread:
http://www.poolforum.com/pf2/showthread.php/22346
before your wiring is done.